The World Bank's board approved $375.9 million for Pakistan's Grid Stability Enhancement Project, the first phase of a ten-year transmission programme. It pays for grid-stabilising equipment at three 500-kilovolt substations and at 26 other substations, and is meant to bring 640 megawatts of currently unused wind power onto the network. Separately, on 7 August the power regulator added 75 paisa a unit to August electricity bills.
- The World Bank approved $375.9 million for the Grid Stability Enhancement Project. It is phase one of a ten-year programme called Boosting Energy Security through Transmission in Pakistan, or BEST-PAK.
- The money buys hardware, not subsidy. It funds static synchronous compensators, machines that steady voltage on a shaky network, at three 500-kilovolt substations, plus reactors and capacitor banks at 26 grid substations.
- The stated payoff is wind power Pakistan already built but cannot use. Southern Pakistan has 1,840 megawatts of wind capacity; the project aims to unlock 640 megawatts that is currently switched off because the grid cannot carry it, and to make room for about 491 megawatts of new private renewable projects.
- The work sits with the National Transmission and Dispatch Company, the state company that runs the high-voltage network, which is itself being split into successor companies.
- In the same window, consumers were charged more. The National Electric Power Regulatory Authority, or NEPRA, notified a fuel cost adjustment of 75 paisa a unit for August bills, recovering an extra Rs9.8 billion. It applies across consumer categories including K-Electric, but not to lifeline consumers.
- The World Bank says the investment will help reduce electricity costs. No source sets a date, or a figure, for when that would show up on a bill.
